Opening date announced for Terminal C at the Orlando Airport

Orlando International Airport is close to finishing its newest terminal.

Terminal C at the airport has reached the 87% percent completion threshold.

Related: Orlando Airport adds Mad Tea Party Photo-Op for Walt Disney World’s 50th Anniversary

Opening date announced for Terminal C at the Orlando Airport

Below is a list of the scheduled plans:

South Terminal C Opening Date Set

Progress at South Terminal C has reached the 87 percent completion threshold. With construction nearing an end, a preliminary timeline for beginning operations at Terminal C was presented by CEO Phil Brown.

  • February 28, 2022 — Temporary Certificate of Occupancy (TCO)
    • City of Orlando issues a TCO when key life safety systems are accepted for critical areas
  • May 1, 2022 — Substantial Completion
    • The program is substantially complete when it is ready for its intended use to operate
  • May-July 2022 — Operational Readiness
    • Transition from construction to operations: Getting the people familiar with the building/systems and test processes/procedures to ensure a successful opening
  • July 2022 — Start of Operations

Related: ICON Park has the best Santa Claus Experience in Orlando

Check back here on Chip & Co. for the latest theme park and entertainment news updates!

Source

travel graphic


For the BEST in Disney, Universal, Dollywood, and SeaWorld Theme Park News, Entertainment, Merchandise & More follow us on, Facebook, Instagram, Tiktok, and Youtube.